Nym Ct, Sunnybank Hills

An active granny flat project in Sunnybank Hills, Brisbane.

Front elevation drawing for the Sunnybank Hills granny flat project
LocationSunnybank Hills, Brisbane
ProjectGranny flat
Floor area80m²
Layout2 bed · 2 bath
Started 10 Jul 2026
In progress Framing

Project overview

The project, in context.

This granny flat project is located in Sunnybank Hills QLD 4109 and is currently in progress.

The current recorded stage is slab. Further project information and construction updates will be added as the work develops and details become available for publication.

Project record

Construction progress.

Construction stages recorded to date, shown from the most recent update back to where the work began.

Timber frames have been installed, completing the main framing stage. — 8 September 2026 · Framing · Timber Framing Completed
8 September 2026 · Framing · Timber Framing CompletedThe timber wall frames and roof trusses have been installed, completing the main framing stage.
Kordon termite protection barrier installed around the slab at the Sunnybank Hills granny flat site — 23 August 2026 · Termite protection · Kordon barrier installed
23 August 2026 · Termite protection · Kordon barrier installedThe Kordon termite protection barrier has been installed and the project is awaiting main frame construction.
Workers screeding and finishing the freshly poured concrete slab — 11 August 2026 · Slab · Concrete slab completed
11 August 2026 · Slab · Concrete slab completedConcrete was poured and finished, marking the completion of the slab stage.
Steel reinforcement mesh and timber formwork in place across the slab area before the concrete pour — 7 August 2026 · Foundation · Structural inspection completed
7 August 2026 · Foundation · Structural inspection completedThe foundation reinforcement and preparation were completed, and the structural engineer carried out the required inspection before the concrete pour.
Completed stormwater, sewer and water-service pipework following Council inspection — 22 July 2026 · Stormwater, sewer and water services completed · Council inspection passed
22 July 2026 · Stormwater, sewer and water services completed · Council inspection passed
On-site dimension check after the concrete ground piers were completed — 18 July 2026 · Ground piers completed · On-site dimension check
18 July 2026 · Ground piers completed · On-site dimension check
Track loader levelling the site at the start of construction — 10 July 2026 · Construction start · Site levelling
10 July 2026 · Construction start · Site levelling
Backyard site before construction began — 3 July 2026 · Before construction
3 July 2026 · Before construction